Footings to Final: How a Building Inspection Schedule Runs on a Home Project

Published Reading time 4 min

Share
An addition interior at the insulation stage with batts between the studs and no drywall yet.
In this article13 sections
  1. 01What sets the order of inspections?
  2. 02Stage 1: site, footings and foundation
  3. 03Stage 2: rough-in, framing and insulation
  4. 04Stage 3: trade finals, building final and permit close
  5. 05How do the two cities’ sequences compare?
  6. 06Smaller projects have shorter lists
  7. 07What to have ready on inspection day
  8. 08What if work was done without inspections?
  9. 09What are the scheduling steps, in order?
  10. 10What the cited sources do not cover
  11. 11Why the final inspection decides when a permit closes
  12. 12Photo Gallery
  13. 13Cost Guides

The City of Maple Grove, Minnesota says all permitted work requires an inspection, that the permit holder is responsible for calling the Building Inspection Services Department to schedule inspections, and that inspections must be scheduled in advance. It adds that required inspections differ based on the project.

What sets the order of inspections?

For additions, the City of Portland, Oregon says to follow the full inspection sequence starting with erosion control and foundation, continuing through rough-in phases, and ending with final inspections for the new portion of the building.

Portland also says all rough trade inspections (electrical, plumbing, mechanical) must be approved before the 270 Framing inspection can occur.

Stage 1: site, footings and foundation

Maple Grove lists the footing inspection prior to pouring of concrete, the poured wall inspection when forms are in place, and the foundation inspection after excavation is complete and any forms or reinforcing steel is in place.

Portland’s list for additions opens with 215 – Setbacks / Location on Lot, which may require a survey if original property corner pins are not visible, followed by 220 – Footings, 225 – Foundation Walls and 235 – Slab-on-Grade.

Stage 2: rough-in, framing and insulation

Maple Grove lists the framing inspection after framing is in place and rough-in electrical, plumbing, and mechanical have been approved, and the insulation inspection after framing is approved and insulation is in place.

Portland lists 270 – Framing, with a moisture content form required, and 280 – Insulation.

Stage 3: trade finals, building final and permit close

Portland lists 199 – Final Electrical (all devices installed and operational), 399 – Final Plumbing (all fixtures in place and working), 699 – Final Mechanical (HVAC systems complete and functional), 299 – Final Building (Address posted, smoke/CO detectors, handrails, egress, required finishes, decks, etc.) and 999 – Final Permit, which closes the permit officially. Portland says that without the 999 Final Permit inspection, the permit is still under inspection, and that if a permit is without an approved inspection for more than 180 days, it will expire.

How do the two cities’ sequences compare?

The table below sets the stages side by side as each city lists them.

Inspection stages as listed by Maple Grove, Minnesota and Portland, Oregon
Stage Maple Grove, Minnesota Portland, Oregon
Foundation Footing, poured wall and foundation Setbacks, footings, foundation walls and slab-on-grade
Framing After rough-in electrical, plumbing and mechanical are approved After all rough trade inspections are approved
Insulation After framing is approved and insulation is in place 280 – Insulation
Finals Trade finals before the building final Trade finals, final building and 999 – Final Permit

Smaller projects have shorter lists

For decks, Maple Grove lists footings after holes are dug but prior to pouring the concrete, framing if determined by the plan review prior to installing the deck boards, and a final when the deck is complete. For a re-roof final it says printed pictures of ice and water protection must be on-site at the final inspection, and for a re-side final, printed pictures of house wrap must be on-site.

What to have ready on inspection day

Maple Grove says approved (stamped) plans and permit and inspection cards are required on job sites to conduct inspections, and that if the inspector must get into a home, the contractor or adult homeowner must be present.

What if work was done without inspections?

The Town of Old Lyme, Connecticut says its Building Department strives to work with homeowners to help them through the process of obtaining necessary after the fact permits. It says to contact the Building Department to schedule an inspection of the work by the building official to confirm that the work was done according to current building codes, and that if the project involved any electrical work, you must have a licensed electrician inspect the work and certify with an affidavit on their letterhead submitted as the electrical inspection.

What are the scheduling steps, in order?

The steps below follow the two city lists cited here.

  1. Ask your local building department which inspections your permit requires.
  2. Schedule each inspection in advance.
  3. Get the rough trade inspections approved before the framing inspection.
  4. Complete the electrical, mechanical and plumbing finals before the building final.
  5. Ask whether your city has a final permit inspection that closes the permit.

What the cited sources do not cover

The sources cited here give no prices. This article is general information, not legal advice.

Why the final inspection decides when a permit closes

In Portland, Oregon the permit will not be approved and closed until the 999 Final Permit inspection, and a permit without an approved inspection for more than 180 days will expire. Ask your local building department which final inspection closes your permit.

Cost guide

Bathroom Remodel Cost

United States
Smaller update$1,750 to $7,000Typical $4,500
Mid-size project$6,000 to $13,000Typical $9,000
Full remodel$16,500 to $52,500Typical $23,000

National ranges from what U.S. households paid contractors (Census American Housing Survey 2023). Full remodel is the upper quarter of hired projects. Prices as of August 2026. This is an estimate for planning, not a quote or a guaranteed Goodhaus price. Your actual cost depends on your home, your choices and your contractor, and quotes may be lower or higher. Open the cost calculator

Get Free Quotes

Cost guide

Kitchen Remodel Cost

United States
Smaller update$2,250 to $11,500Typical $6,000
Mid-size project$9,000 to $22,000Typical $15,500
Full remodel$28,000 to $90,000Typical $48,000

National ranges from what U.S. households paid contractors (Census American Housing Survey 2023). Full remodel is the upper quarter of hired projects. Prices as of August 2026. This is an estimate for planning, not a quote or a guaranteed Goodhaus price. Your actual cost depends on your home, your choices and your contractor, and quotes may be lower or higher. Open the cost calculator

Get Free Quotes

Cost guide

Room Addition Cost

United States
300 sq ft addition$36,000 to $85,000

Room additions are estimated from the cost per square foot of new contractor-built houses (U.S. Census Bureau), an experimental comparison, so only a range is shown. Prices as of August 2026. This is an estimate for planning, not a quote or a guaranteed Goodhaus price. Your actual cost depends on your home, your choices and your contractor, and quotes may be lower or higher. Open the cost calculator

Get Free Quotes