Article
Footings to Final: How a Building Inspection Schedule Runs on a Home Project

In this article13 sections
- 01What sets the order of inspections?
- 02Stage 1: site, footings and foundation
- 03Stage 2: rough-in, framing and insulation
- 04Stage 3: trade finals, building final and permit close
- 05How do the two cities’ sequences compare?
- 06Smaller projects have shorter lists
- 07What to have ready on inspection day
- 08What if work was done without inspections?
- 09What are the scheduling steps, in order?
- 10What the cited sources do not cover
- 11Why the final inspection decides when a permit closes
- 12Photo Gallery
- 13Cost Guides
The City of Maple Grove, Minnesota says all permitted work requires an inspection, that the permit holder is responsible for calling the Building Inspection Services Department to schedule inspections, and that inspections must be scheduled in advance. It adds that required inspections differ based on the project.
What sets the order of inspections?
For additions, the City of Portland, Oregon says to follow the full inspection sequence starting with erosion control and foundation, continuing through rough-in phases, and ending with final inspections for the new portion of the building.
Portland also says all rough trade inspections (electrical, plumbing, mechanical) must be approved before the 270 Framing inspection can occur.
Stage 1: site, footings and foundation
Maple Grove lists the footing inspection prior to pouring of concrete, the poured wall inspection when forms are in place, and the foundation inspection after excavation is complete and any forms or reinforcing steel is in place.
Portland’s list for additions opens with 215 – Setbacks / Location on Lot, which may require a survey if original property corner pins are not visible, followed by 220 – Footings, 225 – Foundation Walls and 235 – Slab-on-Grade.
Stage 2: rough-in, framing and insulation
Maple Grove lists the framing inspection after framing is in place and rough-in electrical, plumbing, and mechanical have been approved, and the insulation inspection after framing is approved and insulation is in place.
Portland lists 270 – Framing, with a moisture content form required, and 280 – Insulation.
Stage 3: trade finals, building final and permit close
Portland lists 199 – Final Electrical (all devices installed and operational), 399 – Final Plumbing (all fixtures in place and working), 699 – Final Mechanical (HVAC systems complete and functional), 299 – Final Building (Address posted, smoke/CO detectors, handrails, egress, required finishes, decks, etc.) and 999 – Final Permit, which closes the permit officially. Portland says that without the 999 Final Permit inspection, the permit is still under inspection, and that if a permit is without an approved inspection for more than 180 days, it will expire.
How do the two cities’ sequences compare?
The table below sets the stages side by side as each city lists them.
| Stage | Maple Grove, Minnesota | Portland, Oregon |
|---|---|---|
| Foundation | Footing, poured wall and foundation | Setbacks, footings, foundation walls and slab-on-grade |
| Framing | After rough-in electrical, plumbing and mechanical are approved | After all rough trade inspections are approved |
| Insulation | After framing is approved and insulation is in place | 280 – Insulation |
| Finals | Trade finals before the building final | Trade finals, final building and 999 – Final Permit |
Smaller projects have shorter lists
For decks, Maple Grove lists footings after holes are dug but prior to pouring the concrete, framing if determined by the plan review prior to installing the deck boards, and a final when the deck is complete. For a re-roof final it says printed pictures of ice and water protection must be on-site at the final inspection, and for a re-side final, printed pictures of house wrap must be on-site.
What to have ready on inspection day
Maple Grove says approved (stamped) plans and permit and inspection cards are required on job sites to conduct inspections, and that if the inspector must get into a home, the contractor or adult homeowner must be present.
What if work was done without inspections?
The Town of Old Lyme, Connecticut says its Building Department strives to work with homeowners to help them through the process of obtaining necessary after the fact permits. It says to contact the Building Department to schedule an inspection of the work by the building official to confirm that the work was done according to current building codes, and that if the project involved any electrical work, you must have a licensed electrician inspect the work and certify with an affidavit on their letterhead submitted as the electrical inspection.
What are the scheduling steps, in order?
The steps below follow the two city lists cited here.
- Ask your local building department which inspections your permit requires.
- Schedule each inspection in advance.
- Get the rough trade inspections approved before the framing inspection.
- Complete the electrical, mechanical and plumbing finals before the building final.
- Ask whether your city has a final permit inspection that closes the permit.
What the cited sources do not cover
The sources cited here give no prices. This article is general information, not legal advice.
Why the final inspection decides when a permit closes
In Portland, Oregon the permit will not be approved and closed until the 999 Final Permit inspection, and a permit without an approved inspection for more than 180 days will expire. Ask your local building department which final inspection closes your permit.
Photo Gallery
Cost guide
Bathroom Remodel Cost
United StatesNational ranges from what U.S. households paid contractors (Census American Housing Survey 2023). Full remodel is the upper quarter of hired projects. Prices as of August 2026. This is an estimate for planning, not a quote or a guaranteed Goodhaus price. Your actual cost depends on your home, your choices and your contractor, and quotes may be lower or higher. Open the cost calculator
Get Free QuotesCost guide
Kitchen Remodel Cost
United StatesNational ranges from what U.S. households paid contractors (Census American Housing Survey 2023). Full remodel is the upper quarter of hired projects. Prices as of August 2026. This is an estimate for planning, not a quote or a guaranteed Goodhaus price. Your actual cost depends on your home, your choices and your contractor, and quotes may be lower or higher. Open the cost calculator
Get Free QuotesCost guide
Room Addition Cost
United StatesRoom additions are estimated from the cost per square foot of new contractor-built houses (U.S. Census Bureau), an experimental comparison, so only a range is shown. Prices as of August 2026. This is an estimate for planning, not a quote or a guaranteed Goodhaus price. Your actual cost depends on your home, your choices and your contractor, and quotes may be lower or higher. Open the cost calculator
Get Free Quotes









